Tender sum£4,120,400accepted 04.03.26
Committed£3,884,11094.3% of tender
Forecast final£4,206,880+£86,480 over
Retention held£206,0205% to practical completion
1,340 mm — sheet width at 1:50

Schedule of quantities — substructure

Rev C
ItemDescriptionUnitQtyRateAmountVar
D20.10Excavate to reduce level, not exceeding 2 m1,24018.4022,816
D20.20Disposal off site, inert1,24026.1032,364
E10.05Mass concrete fill, C20/25188142.0026,696+41 m³
E30.10Reinforcement, high yield, 16 mmt14.21,880.0026,696
E20.15Formwork to sides of foundations41262.5025,750+68 m²
F10.20Blockwork below dpc, 140 mm30688.0026,928

Revision C: two items increased following the ground investigation of 11 May. Both are marked with a revision cloud on drawing 204.